061-6522484 info@mallofmultan.com

Electrical Work Status

 [cincopa AILAaFNhdmbC] Electrical Work Status Lower Ground and Upper Ground floor’s work is 100 percent Completed. 50 percent at 4th floor is completed. Order has been placed for substation bus trunking system. Electric Work for Upper Ground, 4th, 5th floor will be completed by April...

Structure Work Status

[cincopa AwLAVGdjmO1I] Structure has been completed 100% along with cinema. External plastering & Floor work will be started in next month and it will be completed by January 2016. Facade design has been finalized and will be completed by April 2016....

HVAC System

[cincopa A0NAyEd8mGoG] Chilled water and Package type. 500 and 400 tons respectively. Work has already been started on ground and 4th floor. Order has been placed for plant room equipment. Ground, 4th and 5th including plant room should be completed by and between April...