Electrical Work Status
by Admin | Nov 28, 2015 | Construction Progress |
[cincopa AILAaFNhdmbC] |
Electrical Work Status
- Lower Ground and Upper Ground floor’s work is 100 percent Completed.
- 50 percent at 4th floor is completed.
- Order has been placed for substation bus trunking system.
- Electric Work for Upper Ground, 4th, 5th floor will be completed by April 2016.
|